Commuters and businesses near Belize City’s Swing Bridge can expect traffic delays as work continues on a temporary crossing that will be used when dismantling of the existing bridge begins. According to the Ministry of Infrastructure Development and Housing, the temporary bridge is approximately eighty percent complete. Chief Engineer Evondale Moody says he met with the contractors this morning to review progress and discuss challenges affecting the work.

Evondale Moody, Chief Engineer, MIDH: “Based on the meeting that I had just this morning with the contractor, Cisco Construction, we anticipate that we will try and finish this bridge structure by the 30th of November. We have some minor setbacks because we have to deal with the utilities that will be traversing this bridge as well, because the existing Swing Bridge itself, it has a fiber optic that runs under the bed of the river, which is the backbone for BTL. And so they need to remove that line and transfer it to this section of the new bridge. In addition to that, we also have a BEL high-tension pole that needs to be relocated in an effort to make the maneuverability for vehicles making right-hand turns from North Front Street onto the bridge much easier. So those are being sorted out today. As you can see, we have the utility companies here today as well finalizing those arrangements. And so we expect that everything should be completed towards the end of November, the latest the first week in December. The procurement process for the new Swing Bridge is based on what we do here in Belize and so once this bridge is completed the procurement process with the Japanese will commence. And so their timeline is based on the completion date for this bridge structure that we’re currently standing on. So, based on my recent discussion with the Japanese once we give them the go-ahead that we have opened this bridge to traffic, immediately thereafter we have to commence the demolition and removal of the existing Swing Bridge. So our aim is to start that part of the project in December, and we have two to three months to complete the removal of that existing structure.”
The temporary crossing will provide a connection across the Haulover Creek while the Swing Bridge is replaced. With construction taking place in a busy part of downtown Belize City, motorists and pedestrians will need to allow extra time when moving through the area. Moody outlined the temporary bridge’s accommodations and the traffic delays commuters can expect.
Evondale Moody, Chief Engineer, MIDH: “At this point in time, we’re about 75 to 80 percent completed. We have completed four of the five spans already. We’re working on the north approach at this point in time, whereby we will be pouring the last section of the concrete for this area, which will create the approach into North Front Street. And thereafter, we’re working on the south side as well where we have Regent Street West. We have created some little delays there due to the fact that we have to replace the existing structure that is located on Regent Street West to improve that bridge structure, and so we want to tie into that from this new bridge as well. And so once we’re finished with that, then we will do the final tie-in on the south side, which will complete the structure.”
Reporter: And we understand, as a result of this, a portion of Regent Street West has been locked off, correct?
Evondale Moody, Chief Engineer, MIDH: “Yes, that is correct. So that was closed today. The contractor intends to remove the deck for that existing bridge, and then we’ll do a final assessment of the two abutments of that bridge structure to determine if those are intact. That bridge on Regent Street West, and then we will proceed as well with the last span of this new bridge that we have at Hyde’s Lane.”
Reporter: Commuters and pedestrians are probably wondering: Will this bridge be a two-way bridge? Will it be one-way? Will it have access for pedestrians to cross? Just clarify that for them so that they are aware.
Interviewee:
Evondale Moody, Chief Engineer, MIDH: “Yes. So, as I’ve mentioned before, a conscious effort was made by Minister Espat for us to change this structure to a two-lane structure. And so that will accommodate traffic from the north side going to the south, and also from the south side going to the north. We have also incorporated pedestrian footpaths on this bridge so we’ll have two of those on either side of the bridge structure, which, as you can see, those are under construction as well. And those should be completed by the end of this month.”
Moody says the temporary bridge is also being built to provide six feet of clearance for boats. He describes that as an improvement over the clearance available beneath the current Swing Bridge. The crossing will serve road users during the replacement works while allowing smaller vessels to pass underneath.